NEW QUESTION 23
What should the business case state about the minimum viable product (MVP)?
- A. That the MVP must go into operational use
- B. When the MVP will be defined
- C. That the MVP is the same as project viability
- D. What the MVP is
Answer: A
NEW QUESTION 24
Which TWO are the purposes of a highlight report?
1. To describe the MoSCoW priority of user stories.
2. To summarize the status of a work package.
3. To summarize the stage status.
4. To report any potential issues and risks
- A. 1 and 2
- B. 1 and 4
- C. 3 and 4
- D. 2 and 3
Answer: C
Explanation:
Reference:
%20by%20them.&text=The%20project%20manager%20also%20uses,the%20project%20board%20could%20help
NEW QUESTION 25
How is the 'tailor to suit the project' principle applied in an agile context?
- A. By flexing what is produced to stay in control and deliver value
- B. By using the Agilometer to assess the project environment
- C. By emphasizing tolerances on what is being delivered
- D. By fitting releases into planned management stages
Answer: A
NEW QUESTION 26
How should product-based planning be used as part of PRINCE2 Agile?
- A. To plan by focusing on the features required
- B. To enable team planning to be predictive
- C. To track progress against the team plan
- D. To create the project plan using empiricism
Answer: A
NEW QUESTION 27
To help with prioritization, what is MOST important when understanding the difference between scope and quality?
- A. Defining non-functional requirements before functional requirements
- B. Combining functional and non-functional requirements
- C. Creating non-functional requirements with user stories
- D. Differentiating functional from non-functional requirements
Answer: D
NEW QUESTION 28
What is the definition of a timebox?
- A. A period where work is carried out to achieve a goal
- B. A description of the rate of progress a team is making
- C. A regular event that looks at how processes can be improved
- D. A tool to write a requirement in the form of who, what and why
Answer: A
NEW QUESTION 29
Which statement about the waterfall methodology definition is CORRECT?
- A. It is a behavior that involves making things transparent
- B. It states that deadlines should not be moved
- C. It has distinct goals for each stage of development
- D. It promotes the use of experiments carried out in a scientific way
Answer: C
NEW QUESTION 30
According to PRINCE2 Agile, which form of communication shows that a team is vibrant and interactive?
- A. Using email to document discussions
- B. Using meeting minutes to share decisions
- C. Using social media to reach more people
- D. Using visualization to display information
Answer: D
NEW QUESTION 31
Which is NOT one of the core concepts of Lean Startup that apply to PRINCE2?
- A. To build, measure, learn from your experiences
- B. To fail fast, if you are going to fail
- C. To use empiricism, based on knowledge that comes from experience
- D. To create a minimum viable product to manage uncertainty
Answer: C
NEW QUESTION 32
Which statement about the 'embrace change' target is CORRECT?
- A. It reduces testing in order to meet deadlines
- B. It reduces the planning of dependencies between projects
- C. It minimizes the time needed to train a new team member
- D. It encourages the customer to raise new ideas
Answer: D
NEW QUESTION 33
Which role is responsible for facilitating the Agilometer assessment?
- A. Customer subject matter expert
- B. Project manager
- C. Project board
- D. Team manager
Answer: B
NEW QUESTION 34
Which two statements are key responsibilities of supplier representative?
1. They highlight areas that the project may impact from a technical perspective.
2. They are partially assigned to the delivery team.
3. They create the project's specialist products.
4. They prioritize requirements.
- A. 1 and 2
- B. 3 and 4
- C. 2 and 3
- D. 1 and 4
Answer: D
NEW QUESTION 35
How does the change theme regard change in PRINCE2 Agile?
- A. As disruptive
- B. As a necessity
- C. As something to be avoided
- D. As inevitable
Answer: D
NEW QUESTION 36
What needs to happen when new detailed requirements are added to a timebox?
- A. Formal change control should be applied
- B. The delivery milestones should be reviewed and re-planned
- C. More people should be added to the delivery team
- D. Requirements of a similar level of effort should be removed
Answer: D
NEW QUESTION 37
Why are team working agreement produced?
- A. To evolve the effectiveness and behaviors of the self-organizing team by agreeing values
- B. To ensure that the delivery team members comply with company policy
- C. To create structure so that the team manager can assess individual performance
- D. To make the team rules visible to the project manager for monitoring purposes
Answer: A
Explanation:
Reference https://publications.axelos.com/prince2agile2016/content.aspx?page=pra_126&showNav=true&expandNav=true
NEW QUESTION 38
What is an epic?
- A. A high-level requirement
- B. A low-level requirement
- C. A detailed feature
- D. A fine-grained user story
Answer: A
NEW QUESTION 39
......
Ultimate Guide to the PRINCE2-Agile-Foundation - Latest Edition Available Now: https://www.exam4labs.com/PRINCE2-Agile-Foundation-practice-torrent.html
2022 Updated Verified Pass PRINCE2-Agile-Foundation Exam - Real Questions & Answers: https://drive.google.com/open?id=1IS0Qs4_QXWWumW3xmMnY8hJyP4bfnG3v