TopicDetails
Topic 1
  • Understand the focus areas in an agile contex
  • Understand key concepts relating to PRINCE2
Topic 2
  • Understand key concepts relating to projects and PRINCE2 Agile
Topic 3
  • Understand how PRINCE2 principles, themes, processes and management products are tailored and/or applied in an agile context
Topic 4
  • Understand the agile ways of working, key terms and techniques

 

NEW QUESTION 26
Which is a purpose of the quality theme?

  • A. To define the specific conditions that enable a product to be usable
  • B. To evaluate whether the project continues to be achievable
  • C. To assess any potential improvements to a product
  • D. To determine how the means of delivering products is communicated

Answer: B

 

NEW QUESTION 27
What is the definition of a timebox?

  • A. A period where work is carried out to achieve a goal
  • B. A description of the rate of progress a team is making
  • C. A regular event that looks at how processes can be improved
  • D. A tool to write a requirement in the form of who, what and why

Answer: A

 

NEW QUESTION 28
In Scrum, what answers the question 'what can be done this sprint?'

  • A. Sprint review
  • B. Sprint planning
  • C. Daily scrum
  • D. Increment

Answer: C

 

NEW QUESTION 29
Which statement explains the setting of the cost tolerance for a project in an agile context?

  • A. Cost tolerance can be fixed and flexed
  • B. Cost tolerance can be fixed or flexed
  • C. Cost tolerance is flexed
  • D. Cost tolerance is fixed

Answer: C

 

NEW QUESTION 30
Which two statements are key responsibilities of supplier representative?
1. They highlight areas that the project may impact from a technical perspective.
2. They are partially assigned to the delivery team.
3. They create the project's specialist products.
4. They prioritize requirements.

  • A. 1 and 2
  • B. 3 and 4
  • C. 2 and 3
  • D. 1 and 4

Answer: D

 

NEW QUESTION 31
According to PRINCE2 Agile, which form of communication shows that a team is vibrant and interactive?

  • A. Using email to document discussions
  • B. Using meeting minutes to share decisions
  • C. Using social media to reach more people
  • D. Using visualization to display information

Answer: D

 

NEW QUESTION 32
Which is a purpose of the 'controlling stage' process?

  • A. To draft the plan for the next stage's work
  • B. To report stage progress to the project board
  • C. To execute and deliver the project product
  • D. To establish whether the project is complete

Answer: B

Explanation:
Reference:
%20remains%20within%20tolerance.&text=Risks%20and%20issues%20are%20kept%20under%20control

 

NEW QUESTION 33
Which statement explains how the 'learn from experience' principle is applied in an agile context?

  • A. It is supported by the 'inspect and adapt' concept
  • B. It provides guidance on mapping PRINCE2 roles to an agile environment
  • C. It integrates releases within management stages
  • D. It focuses on the prioritization and decomposition of requirements

Answer: A

 

NEW QUESTION 34
Which process can take place during a release review workshop?

  • A. Directing a project
  • B. Managing product delivery
  • C. Managing a stage boundary
  • D. Controlling a stage

Answer: B

 

NEW QUESTION 35
What should be decided when configuring PRINCE2 effectively?

  • A. What to significantly change to create the right blend
  • B. What to remove and where to add guidance
  • C. Where to put the emphasis and where to add guidance
  • D. Which areas are not enabled to work with agile

Answer: A

 

NEW QUESTION 36
How does the change theme regard change in PRINCE2 Agile?

  • A. As disruptive
  • B. As a necessity
  • C. As something to be avoided
  • D. As inevitable

Answer: D

 

NEW QUESTION 37
Which is typically used in agile when estimating detailed requirements during sprint planning?

  • A. T-shirt sizing
  • B. Trading
  • C. Rationalism
  • D. Visioning

Answer: C

 

NEW QUESTION 38
How is the 'tailor to suit the project' principle applied in an agile context?

  • A. By flexing what is produced to stay in control and deliver value
  • B. By using the Agilometer to assess the project environment
  • C. By emphasizing tolerances on what is being delivered
  • D. By fitting releases into planned management stages

Answer: A

 

NEW QUESTION 39
Which statement explains the target 'be on time and hit deadlines' for flexible delivery?

  • A. It improves the supplier's reputation with the customer
  • B. It enables team dynamics to remain the same
  • C. It reduces testing in order to meet deadlines
  • D. It sets the project baseline at the correct level

Answer: C

 

NEW QUESTION 40
During which process should release planning be done for the FIRST time?

  • A. Managing product delivery
  • B. Controlling a stage
  • C. Initiating a project
  • D. Managing a stage boundary

Answer: D

 

NEW QUESTION 41
Which statement about the waterfall methodology definition is CORRECT?

  • A. It is a behavior that involves making things transparent
  • B. It states that deadlines should not be moved
  • C. It has distinct goals for each stage of development
  • D. It promotes the use of experiments carried out in a scientific way

Answer: C

 