NEW QUESTION 26
Which is a purpose of the quality theme?
- A. To define the specific conditions that enable a product to be usable
- B. To evaluate whether the project continues to be achievable
- C. To assess any potential improvements to a product
- D. To determine how the means of delivering products is communicated
Answer: B
NEW QUESTION 27
What is the definition of a timebox?
- A. A period where work is carried out to achieve a goal
- B. A description of the rate of progress a team is making
- C. A regular event that looks at how processes can be improved
- D. A tool to write a requirement in the form of who, what and why
Answer: A
NEW QUESTION 28
In Scrum, what answers the question 'what can be done this sprint?'
- A. Sprint review
- B. Sprint planning
- C. Daily scrum
- D. Increment
Answer: C
NEW QUESTION 29
Which statement explains the setting of the cost tolerance for a project in an agile context?
- A. Cost tolerance can be fixed and flexed
- B. Cost tolerance can be fixed or flexed
- C. Cost tolerance is flexed
- D. Cost tolerance is fixed
Answer: C
NEW QUESTION 30
Which two statements are key responsibilities of supplier representative?
1. They highlight areas that the project may impact from a technical perspective.
2. They are partially assigned to the delivery team.
3. They create the project's specialist products.
4. They prioritize requirements.
- A. 1 and 2
- B. 3 and 4
- C. 2 and 3
- D. 1 and 4
Answer: D
NEW QUESTION 31
According to PRINCE2 Agile, which form of communication shows that a team is vibrant and interactive?
- A. Using email to document discussions
- B. Using meeting minutes to share decisions
- C. Using social media to reach more people
- D. Using visualization to display information
Answer: D
NEW QUESTION 32
Which is a purpose of the 'controlling stage' process?
- A. To draft the plan for the next stage's work
- B. To report stage progress to the project board
- C. To execute and deliver the project product
- D. To establish whether the project is complete
Answer: B
Explanation:
Reference:
%20remains%20within%20tolerance.&text=Risks%20and%20issues%20are%20kept%20under%20control
NEW QUESTION 33
Which statement explains how the 'learn from experience' principle is applied in an agile context?
- A. It is supported by the 'inspect and adapt' concept
- B. It provides guidance on mapping PRINCE2 roles to an agile environment
- C. It integrates releases within management stages
- D. It focuses on the prioritization and decomposition of requirements
Answer: A
NEW QUESTION 34
Which process can take place during a release review workshop?
- A. Directing a project
- B. Managing product delivery
- C. Managing a stage boundary
- D. Controlling a stage
Answer: B
NEW QUESTION 35
What should be decided when configuring PRINCE2 effectively?
- A. What to significantly change to create the right blend
- B. What to remove and where to add guidance
- C. Where to put the emphasis and where to add guidance
- D. Which areas are not enabled to work with agile
Answer: A
NEW QUESTION 36
How does the change theme regard change in PRINCE2 Agile?
- A. As disruptive
- B. As a necessity
- C. As something to be avoided
- D. As inevitable
Answer: D
NEW QUESTION 37
Which is typically used in agile when estimating detailed requirements during sprint planning?
- A. T-shirt sizing
- B. Trading
- C. Rationalism
- D. Visioning
Answer: C
NEW QUESTION 38
How is the 'tailor to suit the project' principle applied in an agile context?
- A. By flexing what is produced to stay in control and deliver value
- B. By using the Agilometer to assess the project environment
- C. By emphasizing tolerances on what is being delivered
- D. By fitting releases into planned management stages
Answer: A
NEW QUESTION 39
Which statement explains the target 'be on time and hit deadlines' for flexible delivery?
- A. It improves the supplier's reputation with the customer
- B. It enables team dynamics to remain the same
- C. It reduces testing in order to meet deadlines
- D. It sets the project baseline at the correct level
Answer: C
NEW QUESTION 40
During which process should release planning be done for the FIRST time?
- A. Managing product delivery
- B. Controlling a stage
- C. Initiating a project
- D. Managing a stage boundary
Answer: D
NEW QUESTION 41
Which statement about the waterfall methodology definition is CORRECT?
- A. It is a behavior that involves making things transparent
- B. It states that deadlines should not be moved
- C. It has distinct goals for each stage of development
- D. It promotes the use of experiments carried out in a scientific way
Answer: C
NEW QUESTION 42
......
PRINCE2 PRINCE2-Agile-Foundation Dumps - Secret To Pass in First Attempt: https://www.exam4labs.com/PRINCE2-Agile-Foundation-practice-torrent.html
PRINCE2-Agile-Foundation Dumps - Grab Out For [NEW-2021] PRINCE2 Exam: https://drive.google.com/open?id=1_Nj0BWpUjUZvDggJxR7_wngNYM4x-7JY