Accomplishing the GAQM CSM-001 is an excellent career feat. It compensates you with a distinguished technical certification that makes you a standout in the field of project management. More so, it advances your skills, whether you’re just a team member, a manager, a developer, or a DBA. To top it all, gaining the Certified Scrum Master certification means that you may now enjoy a lucrative salary of around $92,000 a year as per Payscale! So, give your best shot and study the topics diligently by making use of the official E-course and manuals found on Amazon!
NEW QUESTION 33
True or False: Story Points are for sizing, not for time estimation?
- A. False
- B. True
Answer: B
NEW QUESTION 34
The Sprint Backlog is owned by?
- A. The Scrum Master
- B. The Scrum Master and Development Team
- C. The Product Owner
- D. The Development Team
Answer: D
NEW QUESTION 35
The correct sequence of events in using Scrum framework is as follows:
- A. Sprint Planning, Daily Scrum, Sprint, Sprint Review, and Sprint Retrospective
- B. Sprint Planning, Sprint, Sprint Retrospective, Daily Scrum, and Sprint Review
- C. Sprint Planning, Sprint, Sprint Retrospective, Daily Scrum, and Sprint Review
- D. Sprint Planning, Sprint, Daily Scrum, Sprint Review, and Sprint Retrospective
Answer: D
NEW QUESTION 36
Who determines when it is appropriate to update the Sprint Backlog during a Sprint?
- A. The Scrum Team
- B. The Project Manager
- C. The Product Owner
- D. The Development Team
Answer: D
NEW QUESTION 37
What is an ideal size for a Scrum team?
- A. 0
- B. 1
- C. 2
- D. 3
Answer: C
NEW QUESTION 38
When many Scrum Teams are working on a project, what best describes the definition of "done"?
- A. Each Team defines and uses its own
- B. All teams must use the same definition
- C. It depends
- D. Each Team uses its own but must make it clear to all other Teams
Answer: B
NEW QUESTION 39
What is the recommended size for a Development Team?
- A. 0
- B. 7, +2 or -2
- C. 6, +3 or -3
- D. 1
Answer: B
NEW QUESTION 40
The Sprint Goal is selected before the Sprint Backlog is created.
- A. False
- B. True
Answer: B
NEW QUESTION 41
On a new Scrum Team, the Development Team tell the Scrum Master that they don't feel the need for retrospectives. Which answer is correct?
- A. Start doing retrospectives
- B. Discuss with product owner
- C. None of above
Answer: C
Explanation:
Explanation/Reference:
NEW QUESTION 42
___________________is responsible for the Scrum process, facilitate the team and protect the team from outside noise.
- A. Scrum Owner
- B. Stakeholder
- C. Product Owner
- D. Scrum Master
Answer: D
NEW QUESTION 43
You are the Scrum Master and the very first Sprint will complete in 5 days. You are creating a meeting invite for the Sprint Review to demo the items completed in the Sprint. Who should you invite as a required attendee to the Sprint Review?
1. Product Owner(s)
2. Development Team
3. Business Users
- A. 1 only
- B. 1 and 2 only
- C. 1, 2, and 3
- D. The entire company
Answer: B
NEW QUESTION 44
Which three are suggested questions in a daily scrum meeting? (Choose three.)
- A. Why shall I do?
- B. What will I do today?
- C. What impedes me?
- D. Who will be responsible?
- E. What did I do yesterday?
Answer: B,C,E
Explanation:
Explanation/Reference: https://sprint.ly/blog/scrum-meeting-best-practices/
NEW QUESTION 45
Andrea is a very productive team member, but she's always poking around for information and asking for details, especially in areas of the project that she isn't involved in. What should you do?
- A. Tell her to contact a Subject Matter Expert
- B. Tell her to stop being so nosy
- C. Ignore her and hope it goes away
- D. Think about why she's asking questions and try to address the root of the problem
Answer: D
NEW QUESTION 46
When is the Sprint Backlog created?
- A. At the beginning of the project
- B. During the Sprint
- C. During the Sprint Planning meeting
- D. Prior to the Sprint Planning meeting
Answer: D
NEW QUESTION 47
The most encouraged time of day to hold a Scrum Daily Meeting is:
- A. 7:00 PM
- B. A beginning of the day
- C. 4:30 PM
- D. Immediately after lunch
Answer: B
NEW QUESTION 48
___________ can change the priority of items in the _________ backlog at any time.
- A. The Scrum Master; Sprint
- B. The Product Owner(s); Sprint
- C. The Product Owner(s); Product
- D. The Team; Product
Answer: C
NEW QUESTION 49
What is the maximum time that Scrum recommends the team spend in the daily scrum (daily standup)?
- A. Four hours
- B. As long as ittakes
- C. Thirty minutes
- D. One hour
- E. Fifteen minutes
Answer: E
NEW QUESTION 50
Which statement best describes Scrum?
- A. A framework within which complex products in complex environments are developed
- B. A cookbook that defines best practices for software development
- C. A defined and predictive process that conforms to the principles of Scientific Management
- D. A complete methodology that defines how to develop software
Answer: A
NEW QUESTION 51
......