NEW QUESTION # 15
During system testing phase of a word processor, a tester finds that on opening a file from a particular set of files, which are part of a critical workflow, the word processor crashes. Which of the following is the next step the tester should take poor to recording the deviation?
- A. Try to identify the code fragment causing the problem
- B. Try to recreate the incident before reporting
- C. Send an email to the developer and not report the bug
- D. Report the incident as is without any further action
Answer: B
Explanation:
An incident is any event that occurs during testing that requires investigation. An incident report is a document that records the details of an incident. The next step the tester should take prior to recording the deviation is to try to recreate the incident before reporting. This can help confirm that the incident is reproducible and not caused by a random or external factor. This can also help gather more information about the incident, such as the steps to reproduce it, the expected and actual results, the severity and priority of the incident, or any screenshots or logs that can illustrate the incident. Trying to identify the code fragment causing the problem is not the next step the tester should take prior to recording the deviation, as this is a debugging activity that is usually performed by developers after receiving the incident report. Sending an email to the developer and not reporting the bug is not the next step the tester should take prior to recording the deviation, as this is an informal and unstructured way of communicating incidents that can lead to confusion, inconsistency or loss of information. Reporting the incident as is without any further action is not the next step the tester should take prior to recording the deviation, as this can result in incomplete or inaccurate incident reports that can hamper the investigation and resolution of incidents. Verified Reference: A Study Guide to the ISTQB Foundation Level 2018 Syllabus - Springer, Chapter 3, page 32-33.
NEW QUESTION # 16
Software was found lo take much more time than the stated requirement of less than one second to save a file. Upon investigation it was found that there was an unnecessary check inside a loop which was slowing down the file-save operation. The software not being able to meet the desired response time is an example of
- A. Failure
- B. Error
- C. Defect
- D. It is not a defect
Answer: A
Explanation:
A failure is an event in which a component or system does not perform a required function within specified limits. A failure is observable by the software users or other stakeholders. A failure is caused by one or more defects in the software. In this case, the software not being able to meet the desired response time is an example of a failure, as it deviates from the stated requirement and affects the user experience. It is not a defect, which is a flaw in the software that causes the failure. It is not an error, which is a human action that produces an incorrect result. It is not a non-defect, as it clearly violates a specified requirement. Verified Reference: [A Study Guide to the ISTQB Foundation Level 2018 Syllabus - Springer], Chapter 1, page 4.
NEW QUESTION # 17
Which of the following should be included in a test status report?
I Estimation details
II Total number of open and closed defects
III Actual effort spent
IV Defect reports
V Number of executed, failed, blocked tests
- A. III.V
- B. II, III.V
- C. II, III
- D. I. II. IV
Answer: B
Explanation:
The following should be included in a test status report: total number of open and closed defects, actual effort spent, and number of executed, failed, and blocked tests. A test status report is a document that provides information on the results and status of testing activities for a given period or phase. A test status report should include information that is relevant, accurate, and timely for the intended audience and purpose. Some of the information that should be included in a test status report are: total number of open and closed defects, which can indicate the defect trend and defect density of the software product; actual effort spent, which can indicate the productivity and efficiency of the testing process; number of executed, failed, and blocked tests, which can indicate the test progress and test coverage of the software product. The following should not be included in a test status report: estimation details, defect reports, and impact analysis. Estimation details are not part of a test status report, but rather part of a test plan or a test estimation document. Estimation details provide information on the expected time, resources, and costs for testing activities, not on the actual results or status of testing activities. Defect reports are not part of a test status report, but rather separate documents that provide detailed information on individual defects found during testing. Defect reports include information such as defect description, defect severity, defect priority, defect status, defect resolution, etc. Defect reports can be referenced or summarized in a test status report, but not included in full. Impact analysis is not part of a test status report, but rather part of a risk assessment or prioritization process. Impact analysis provides information on the potential effects or consequences of a change or a defect on the software product or project. Impact analysis can be used to evaluate the amount or scope of testing to be performed, but not to report the results or status of testing activities. Verified Reference: A Study Guide to the ISTQB Foundation Level 2018 Syllabus - Springer, page 141.
NEW QUESTION # 18
Which of the following statements about re-testing and regression testing are TRUE?
I Re-testing should be performed after a defect is fixed.
II Regression testing should always be performed after a defect is fixed.
III Re-testing and regression testing may be performed at any test level.
IV Regression testing may include functional, non-functional and structural testing.
V Re-testing should be included in the debugging activity.
- A. I, Ill
- B. I, III. Iv
- C. II. IV, V
- D. II, v
Answer: B
Explanation:
The following statements about re-testing and regression testing are true:
I) Re-testing should be performed after a defect is fixed. Re-testing is a type of testing that verifies that a defect has been successfully resolved by executing a test case that previously failed due to that defect. Re-testing should be performed after a defect is fixed and delivered to ensure that it does not cause any new failures or side effects.
III) Re-testing and regression testing may be performed at any test level. Re-testing and regression testing are not limited to a specific test level, but can be applied at any level depending on the context and objectives. For example, re-testing and regression testing can be performed at unit level, integration level, system level or acceptance level.
IV) Regression testing may include functional, non-functional and structural testing. Regression testing is a type of testing that verifies that previously tested software still performs correctly after changes. Regression testing may include various types of testing depending on the scope and purpose of the changes. For example, regression testing may include functional testing to check if the software meets its requirements, non-functional testing to check if the software meets its quality attributes, or structural testing to check if the software meets its design or code standards. The following statement about re-testing and regression testing is false:
II) Regression testing should always be performed after a defect is fixed. Regression testing is not always necessary after a defect is fixed, as some defects may have a low impact or low likelihood of affecting other parts of the software. Regression testing should be performed after a defect is fixed only if there is a risk of introducing new defects or causing existing defects due to the changes made to fix the defect. Verified Reference: A Study Guide to the ISTQB Foundation Level 2018 Syllabus - Springer, Chapter 2, page 19; Chapter 4, page 45.
NEW QUESTION # 19
Consider the following statements about risk-based testing.
I) Risk-based testing has the objective to reduce the level of protect risks.
II) Tests should be prioritized to find tie critical detects as early as possible.
III) Non-testing activities may also help to reduce risk
IV) Risks have to be reassessed on a regular basis.
V) The project stakeholders can give useful input to determine the risks
- A. II, Ill and V are true. 1 ants Iv are false.
- B. II, III IV and V are correct. I is false.
- C. I III IV and V are true. II is false.
- D. I, II and IV are true. III and V are false.
Answer: B
Explanation:
The following statements about risk-based testing are correct:
II) Tests should be prioritized to find tie critical detects as early as possible. Risk-based testing involves prioritizing tests based on risk level, which reflects both the likelihood and impact of defects or failures. Tests with higher risk level should be executed earlier than tests with lower risk level, in order to find and fix critical defects as soon as possible.
III) Non-testing activities may also help to reduce risk. Risk-based testing does not only involve testing activities, but also other activities that can help mitigate risks, such as reviews, inspections, audits, simulations or prototyping.
NEW QUESTION # 20
In what way do Configuration Management effects testing?
- A. There is very little influence of configuration management practices on the test project.
- B. Configuration management is important for developers, not for testers
- C. Without proper configuration management, test planning cannot proceed.
- D. Proper configuration management ensures that testers can uniquely identity the tested item
Answer: D
Explanation:
Configuration management is a process that establishes and maintains consistency among work products throughout their life cycle. Configuration management affects testing in various ways, such as:
Proper configuration management ensures that testers can uniquely identify the tested item, which can help traceability, reproducibility and accountability.
Proper configuration management ensures that testers have access to consistent versions of software components and testware, which can help reliability, compatibility and efficiency.
Proper configuration management ensures that testers can track changes and defects in software components and testware, which can help verification, validation and reporting.
Proper configuration management ensures that testers can control the configuration of the test environment, which can help stability, security and performance. Configuration management is not a prerequisite for test planning, as test planning can proceed without configuration management, although it may be less effective or accurate. Configuration management is not important for developers only, but for testers as well, as it affects the quality and consistency of the testing process and products. Configuration management has a significant influence on the test project, as it affects various aspects of testing, such as traceability, reproducibility, reliability, compatibility, efficiency, verification, validation, reporting, stability, security and performance. Verified Reference: A Study Guide to the ISTQB Foundation Level 2018 Syllabus - Springer, Chapter 6, page 60-61.
NEW QUESTION # 21
A team's test strategy was to invest equal effort in testing each of a system's modules. After running one test cycle, it turned out that most of the critical bugs were detected in one of the system's modules.
Which testing principal suggests a change to the current test strategy for the next test cycle?
- A. Pesticide Paradox
- B. Early testing
- C. Absence-of-errors fallacy
- D. Defect clustering
Answer: D
Explanation:
Defect clustering is a testing principle that states that a small number of modules contain most of the defects detected during pre-release testing, or are responsible for most of the operational failures. Defect clustering can be explained by Pareto's principle (also known as the 80-20 rule), which states that approximately 80% of the problems are found in 20% of the modules. Defect clustering suggests a change to the current test strategy for the next test cycle, as it implies that more effort should be allocated to test the modules that have shown high defect density or criticality. Pesticide paradox is another testing principle that states that if the same tests are repeated over and over again, eventually they will no longer find any new defects. Pesticide paradox suggests a change to the current test strategy for the next test cycle, but not based on defect clustering, but rather on test diversity and coverage. Early testing is a testing principle that states that testing activities should start as early as possible in the software development life cycle and should be focused on defined objectives. Early testing does not suggest a change to the current test strategy for the next test cycle, but rather a proactive approach to prevent defects from occurring or propagating. Absence-of-errors fallacy is a testing principle that states that finding and fixing defects does not help if the system built is unusable and does not fulfill the users' needs and expectations. Absence-of-errors fallacy does not suggest a change to the current test strategy for the next test cycle, but rather a focus on quality attributes and user requirements. Verified Reference: A Study Guide to the ISTQB Foundation Level 2018 Syllabus - Springer, Chapter 1, page 9-10.
NEW QUESTION # 22
Consider the following testing levels:
1) Component Testing
2) Integration Testing
3) System Testing
4) Acceptance Testing
Which of the following statements is true?
- A. All the testing levels are applicable to V-model for software development.
Only acceptance testing is applicable for iterative models. - B. Acceptance testing is applicable for all software development models.
Component and system testing are applicable only for the V-model. - C. All testing levels are applicable, independent of which software development life-cycle process (V-model. iterative, incremental) is used.
- D. Integration and system testing are applicable when V-model is used.
Component and acceptance testing are applicable when iterative development models are used.
Answer: C
Explanation:
All testing levels are applicable, independent of which software development life-cycle process (V-model, iterative, incremental) is used. Testing levels are defined based on the scope and objectives of testing, not on the software development model. Component testing, integration testing, system testing and acceptance testing are common testing levels that can be applied to any software development model, as long as they are planned and executed properly. The V-model is a software development model that emphasizes the relationship between each development phase and its corresponding testing phase. Iterative and incremental models are software development models that divide the development process into smaller cycles or iterations, where each iteration produces a working version of the software that can be tested and evaluated. Verified Reference: A Study Guide to the ISTQB Foundation Level 2018 Syllabus - Springer, page 18.
NEW QUESTION # 23
Manager responsibilities in formal review includes ad except one of the following:
- A. Planning the review
- B. Decide on the execution of reviews
- C. Determines if the review objectives have been met
- D. Allocate time for review
Answer: C
Explanation:
A formal review is a type of review that follows a defined process with formal entry and exit criteria and roles and responsibilities for participants. A formal review can have various roles involved, such as manager, moderator, author, reviewer and scribe. The manager responsibilities in formal review include all except one of the following:
Planning the review (correct responsibility)
Determines if the review objectives have been met (incorrect responsibility) Decide on the execution of reviews (correct responsibility) Allocate time for review (correct responsibility) The responsibility of determining if the review objectives have been met belongs to the moderator role, not to the manager role. Verified Reference: [A Study Guide to the ISTQB Foundation Level 2018 Syllabus - Springer], Chapter 3, page 28-29.
NEW QUESTION # 24
A bank software has a feature of locking down accounts that have and overdraft higher than $10,000.
Due to a bug in the code, the system locks down accounts once they reached $1000 overdraft.
Based on this context, which of the following is correct statement
- A. It is an example of a defect, that if goes undetected, will cause harm to the end customer but not to the company (the bank)
- B. It is an example of a defect that if goes undetected, will not cause any real harm to either the end customer or to the company (the bank)
- C. It is an example of a defect that it goes undetected, will cause harm to the end customer and to the company (the bank)
- D. It is an example of a defect that if goes undetected, will not cause harm to the end customer, but will cause harm to the company (the bank)
Answer: C
Explanation:
A defect is a flaw in a component or system that can cause the component or system to fail to perform its required function. A defect can cause harm to the end customer, the company, or both, depending on the impact and severity of the failure. In this case, the defect in the code causes the system to lock down accounts that have an overdraft higher than $1000, instead of $10,000. This can cause harm to the end customer, as they may lose access to their funds and face inconvenience or financial difficulties. This can also cause harm to the company, as they may lose customer trust and satisfaction, face legal issues or complaints, or incur additional costs for fixing the defect and restoring the accounts. Verified Reference: [A Study Guide to the ISTQB Foundation Level 2018 Syllabus - Springer], Chapter 1, page 3-4.
NEW QUESTION # 25
Which of the following is NOT a deciding factor m determining the extent of testing required?
- A. Time available to do testing
- B. Budget to do testing
- C. A particular tester involved in testing
- D. Level of risk of the product or features
Answer: C
Explanation:
The extent of testing required for a software product depends on various factors, such as the level of risk, the budget, and the time available. The level of risk reflects the potential impact of failures on the stakeholders and the environment. The budget determines how much resources can be allocated for testing. The time available defines the schedule and deadlines for testing activities. The particular tester involved in testing is not a deciding factor for the extent of testing required, as testing should be based on objective criteria and not on personal preferences or abilities. Verified Reference: [A Study Guide to the ISTQB Foundation Level 2018 Syllabus - Springer], Chapter 2, page 14-15.
NEW QUESTION # 26
Which of the following statements about independent testing is WRONG?
- A. Independent testing is necessary because developers don't know any testing.
- B. A certain degree of independence makes the tester more effective at finding defects.
- C. Independent testing is best suited for the system test level.
- D. Independent test teams may find other types of detects than developers who are familiar with the system's structure.
Answer: A
Explanation:
Independent testing is testing performed by a person or group that is independent of the development team. Independent testing can have various degrees of independence, ranging from testers who are part of the same organization as developers to testers who are external contractors or consultants. Independent testing can have various benefits, such as reducing bias, increasing objectivity, improving quality, or providing different perspectives. Independent testing is not necessary because developers don't know any testing, as this is a wrong and disrespectful statement. Developers can perform various types of testing, such as unit testing, component testing, or integration testing. However, independent testing can complement developer testing by providing additional levels of verification and validation, such as system testing, acceptance testing, or non-functional testing. Verified Reference: [A Study Guide to the ISTQB Foundation Level 2018 Syllabus - Springer], Chapter 2, page 16-17.
NEW QUESTION # 27
In maintenance testing, what is the relationship between impact analysis and regression testing?
- A. There is no relationship between impact analysis and regression testing.
- B. The impact analysis is used to evaluate the amount of regression testing to be performed.
- C. Impact analysis requires a regression testing for all program elements which were newly integrated (new functionalities).
- D. Impact analysis requires a regression testing for only the tests that have detected faults in previous SW release
Answer: B
Explanation:
In maintenance testing, the relationship between impact analysis and regression testing is that the impact analysis is used to evaluate the amount of regression testing to be performed. Maintenance testing is a type of testing that is performed on an existing software product after it has been delivered or deployed, in order to ensure that it still meets its requirements and functions correctly after a change or a modification. Maintenance testing can be triggered by various reasons, such as corrective maintenance (fixing defects), adaptive maintenance (adapting to new environments), perfective maintenance (improving performance), preventive maintenance (avoiding future problems), etc. Impact analysis is a technique that is used to assess the extent and nature of changes introduced by maintenance activities on the software product or project. Impact analysis helps to identify which parts of the software product are affected by the changes, which parts need to be modified or updated accordingly, which parts need to be retested or verified for correctness or compatibility, etc. Regression testing is a type of testing that verifies that previously tested software still performs correctly after a change or a modification. Regression testing helps to detect any side effects or unintended consequences of maintenance activities on the software product's functionality or quality. Regression testing can be performed at various levels and scopes depending on the impact analysis results. Therefore, in maintenance testing, impact analysis is used to evaluate the amount of regression testing to be performed. Verified Reference: A Study Guide to the ISTQB Foundation Level 2018 Syllabus - Springer, page 20.
NEW QUESTION # 28
Which of the following statements regarding inspection is NOT true?
- A. An inspection may be led by a trained moderator who shall not be the author.
- B. An inspection can be performed by peers.
- C. An inspection shall follow a formal process based on rules and checklists with entry and exit criteria
- D. The main purpose of an inspection is to find solutions to the problems.
Answer: D
Explanation:
An inspection is a type of review that follows a defined process with formal entry and exit criteria and roles and responsibilities for participants. An inspection can be performed by peers with different roles, such as moderator, author, reviewer and scribe. The following statement about inspection is not true:
B) The main purpose of an inspection is to find solutions to the problems. This statement is not true, as the main purpose of an inspection is to find defects or issues in a work product, not to find solutions to the problems. Finding solutions to the problems is a debugging or problem-solving activity that is usually performed by the author or developer after receiving the inspection report. The following statements about inspection are true:
A) An inspection may be led by a trained moderator who shall not be the author. This statement is true, as an inspection requires a moderator role who leads the inspection process and ensures that it follows the rules and standards. The moderator should be trained in inspection techniques and should not be the author of the work product under inspection, in order to avoid bias or conflict of interest.
C) An inspection can be performed by peers. This statement is true, as an inspection involves peer review, which means that the work product under inspection is evaluated by people who have similar roles or expertise as the author, but who are not directly involved in creating or modifying the work product.
D) An inspection shall follow a formal process based on rules and checklists with entry and exit criteria. This statement is true, as an inspection follows a formal process that consists of six main steps: planning, kick-off meeting, individual preparation, review meeting, rework and follow-up. Each step has defined rules and checklists to guide the participants and ensure consistency and quality. Each step also has entry and exit criteria to ensure that the prerequisites and objectives are met before moving to the next step. Verified Reference: A Study Guide to the ISTQB Foundation Level 2018 Syllabus - Springer, Chapter 3, page 28-29.
NEW QUESTION # 29
Which of the following statements is CORRECT?
- A. Test cases are sequences of actions for test execution specified during the test implementation activity D. Test cases are derived during the test design activity to cover test objectives or test conditions
- B. Test cases describe items or events to test that are derived from the test basis during the test analysis activity
- C. Test cases are made up of input values, expected results and actual results developed to cover test objectives
Answer: A
Explanation:
A test case is a set of input values, execution preconditions, expected results and execution postconditions, developed for a particular objective or test condition. A test case is a sequence of actions for test execution that can be followed by a tester or a test automation tool. A test case is specified during the test implementation activity, which is the activity that prepares the testware needed for test execution. A test case does not include actual results, as these are obtained during test execution and compared with the expected results. A test case does not describe items or events to test, as these are derived from the test basis during the test analysis activity. A test case is not derived during the test design activity, as this is the activity that specifies the test conditions or objectives that need to be tested. Verified Reference: [A Study Guide to the ISTQB Foundation Level 2018 Syllabus - Springer], Chapter 3, page 23-24; Chapter 4, page 34.
NEW QUESTION # 30
The following sentences refer to the 'Standard for Software Test Documentation' specification (IEEE 829).
Which sentence is correct?
- A. The key to high quality test documentation regimes is strict adherence to this standard
- B. This test plan outline is relevant for military projects. For consumer market projects there is a different specification with fewer items.
- C. Any deviation from this standard should be approved by management, marketing & development
- D. Most test documentation regimes follow this spec to some degree, with changes done to fit a specific situation or organization
Answer: D
Explanation:
The IEEE 829 standard is a widely used specification for test documentation, but it is not mandatory or universal. Most test documentation regimes follow this spec to some degree, with changes done to fit a specific situation or organization. The standard does not require any approval from management, marketing or development for any deviation, nor does it depend on the type of project (military or consumer market). The standard also does not guarantee high quality test documentation regimes, as it only provides a general outline and format, not the actual content or quality criteria. Verified Reference: A Study Guide to the ISTQB Foundation Level 2018 Syllabus - Springer, page 16.
NEW QUESTION # 31
Which of the following is the most important task of a typical test leader?
- A. To prepare and acquire test data.
- B. To coordinate the test strategy with project managers.
- C. To automate tests.
- D. To set up the test environment.
Answer: B
Explanation:
The most important task of a typical test leader is to coordinate the test strategy with project managers. The test strategy is a high-level document that defines the general approach and objectives of testing for a project or an organization. The test leader is responsible for defining, documenting, communicating, and implementing the test strategy in alignment with the project goals and constraints. The test leader also needs to coordinate with project managers and other stakeholders to ensure that the test strategy is feasible, effective, and efficient. The other options are not the most important tasks of a typical test leader. To automate tests is a task of a test automation engineer or a test automation specialist. To prepare and acquire test data is a task of a test analyst or a test engineer. To set up the test environment is a task of a test environment manager or a test environment specialist. Verified Reference: A Study Guide to the ISTQB Foundation Level 2018 Syllabus - Springer, page 13.
NEW QUESTION # 32
Which of the following statements about test reports are TRUE?
I Test reports shall be approved by the test team.
II Test reports shall give stakeholders information as basis for decisions.
Ill Test reports shall summarize what happened through a period of testing.
IV Test reports shall be approved by the development team, the test team and the customer V Test reports shall include information about remaining risks.
- A. II, III, V
- B. II, III, IV
- C. I, III, v
- D. I, II, IV
Answer: A
Explanation:
Statements II, III and V are true about test reports. Test reports are documents that provide information on the results and status of testing activities for a given period or phase. Test reports should give stakeholders information as basis for decisions, such as whether to release the software product, whether to continue testing, whether to change the scope or priorities of testing, etc. Test reports should summarize what happened through a period of testing, such as what test cases were executed, what defects were found, what risks were identified, what issues were encountered, what achievements were made, etc. Test reports should include information about remaining risks, such as what defects are still open, what test cases are still pending, what functionalities are still untested, what uncertainties are still unresolved, etc. Statements I and IV are not true about test reports. Test reports do not need to be approved by the test team, the development team, or the customer, unless it is specified by the test policy or the test plan. Test reports only need to be reviewed and verified by the test leader or the test manager before being distributed to the intended recipients. Verified Reference: A Study Guide to the ISTQB Foundation Level 2018 Syllabus - Springer, page 141.
NEW QUESTION # 33
The following incident report that was generated during test of a web application.
What would you suggest as the most important report improvement?
Defect detected date: 15 8.2010
Defect detected by: Joe Smith
Test level System test
Test case: Area 5/TC 98
Build version: 2011-16.2
Defect description After having filled out all required fields in screen 1, t click ENTER to continue to screen 2 Nothing happens, no system response at all.
- A. Add information about which developer should fix the bug
- B. Add the time stamp when the incident happened
- C. Add information about which web browser was used
- D. Add an impact analysis
Answer: C
Explanation:
The most important report improvement for the given incident report would be to add information about which web browser was used when the defect was detected. This information is relevant for reproducing and debugging the defect, as different web browsers may have different behaviors or compatibility issues with the web application. The other options are less important or irrelevant for the incident report. The developer who should fix the bug can be assigned by the project manager or the defect tracking system, not by the tester who reports the defect. The time stamp when the incident happened is not very useful, as it does not indicate the cause or the frequency of the defect. The impact analysis is not part of the incident report, but rather of the risk assessment or prioritization process. Verified Reference: A Study Guide to the ISTQB Foundation Level 2018 Syllabus - Springer, page 140.
NEW QUESTION # 34
For withdrawing money tram an Automated Teller Machine (ATM), the following conditions are required:
- The bank card is valid
- The PIN code is correct
- Money is available in the user's account
The following are some possible interactions between the user and the ATM:
- The entered card is invalid The card is rejected
- The PIN code is wrong The ATM asks for another PIN code
- The requested amount is more than available in the user's account: The ATM asks for another amount
- The requested amount is available in the user's account The ATM dispenses the money Which test design technique should be used to cover all possible combinations of the input conditions?
- A. Decision table
- B. Boundary value analysis
- C. Equivalence class partitioning
- D. Use case based testing
Answer: A
Explanation:
A decision table is a technique that should be used to cover all possible combinations of input conditions for withdrawing money from an Automated Teller Machine (ATM). A decision table shows combinations of inputs and/or stimuli (causes) with their associated outputs and/or actions (effects). A decision table consists of four quadrants: conditions (inputs), actions (outputs), condition entries (values) and action entries (results). A decision table can be used to test components that have multiple inputs and outputs that depend on logical combinations of conditions. For example, for testing the ATM, we can identify three input conditions: the bank card is valid, the PIN code is correct, and money is available in the user's account. We can also identify four output actions: the card is rejected, the ATM asks for another PIN code, the ATM asks for another amount, and the ATM dispenses the money. A decision table can show all possible combinations of these conditions and actions in a systematic way.
Use case based testing is not a technique that can cover all possible combinations of input conditions for withdrawing money from an ATM. Use case based testing is a technique that verifies that a software product or system meets its specified requirements or user stories by executing realistic scenarios or workflows. Use case based testing can be used to test components that have complex or dynamic interactions with users or other systems. For example, for testing the ATM, we can identify several use cases, such as withdraw money, check balance, transfer money, etc. Each use case can have one or more scenarios that describe the steps and outcomes of the interaction. However, use case based testing may not cover all possible combinations of input conditions, as some scenarios may be omitted or overlooked.
Boundary value analysis is not a technique that can cover all possible combinations of input conditions for withdrawing money from an ATM. Boundary value analysis is a technique that tests boundary values between partitions of equivalent data. Boundary values are values at the edge of an equivalence partition or at the smallest incremental distance on either side of an edge. Boundary value analysis can be used to test components that have input values that can be divided into partitions of equivalent data. For example, for testing the ATM, we can identify boundary values for the input amount, such as the minimum and maximum amount allowed by the system or the user's account. However, boundary value analysis may not cover all possible combinations of input conditions, as some conditions may not have boundary values or may not be related to input values.
Equivalence class partitioning is not a technique that can cover all possible combinations of input conditions for withdrawing money from an ATM. Equivalence class partitioning is a technique that divides the input data and output results of a software component into partitions of equivalent data. Each partition should contain data that is treated in the same way by the component. Equivalence class partitioning can be used to test components that have input values that can be divided into partitions of equivalent data. For example, for testing the ATM, we can identify equivalence partitions for the input amount, such as valid amount (within the range allowed by the system and the user's account) and invalid amount (outside the range allowed by the system or the user's account). However, equivalence class partitioning may not cover all possible combinations of input conditions, as some conditions may not be related to input values or may have more than two partitions. Verified Reference: [A Study Guide to the ISTQB Foundation Level 2018 Syllabus - Springer], Chapter 4, page 34-46.
NEW QUESTION # 35
The following requirement is given "Set X to be the sum of Y and Z".
All the following four implementations have bugs.
Which one of the following bugs can be caught by Static Analysis?
- A. int x = 1.
Int y = 2.
Int z = 3.
Z = x +y - B. int y = 2
Int z = 3.
Y = z+y - C. int x = 1.
int y = 2.
int y = 3.
X = y=z; - D. int x = 1.
int y = 2.
int z = 3.
X = z-y
Answer: C
Explanation:
Static analysis is a technique that analyzes the source code or other software artifacts without executing them. Static analysis can detect defects such as syntax errors, coding standards violations, potential security vulnerabilities, or logical flaws. Static analysis can catch the bug in the first implementation, as it contains two syntax errors: the variable y is declared twice, and the assignment statement X = y=z is invalid. Static analysis cannot catch the bugs in the other three implementations, as they are logical errors that do not violate any syntax rules, but produce incorrect results. Verified Reference: [A Study Guide to the ISTQB Foundation Level 2018 Syllabus - Springer], Chapter 3, page 25-26.